Number of panels HT72-18X (ND) 590W Topcon Double: 3,384 12 pcs
Number of inverters Sungrow SG125CX-P2: 12 pcs
Number of inverters Sungrow SG50CX-P2: 2 pcs
Total power: 2*998,280 W
Performance guarantee: 25 years
Power plant type: ground-based
Turnkey construction period: 2 months
Commissioning: June 2025